Watch our progress on the Saint Marys Project.
  • Donna Asbell, Project Manager

  • Thomas Home Improvement, General Contractor
Extra Hours
1.888.773.9872
Originally this house was
1600 square feet.  We
are doubling the square
footage by adding a
second floor.  There will
be a wrap around porch
on three sides.

Project is expected to
take abut 20 weeks.  
These pictures are
before any construction.
This is about week 10.  
Progress has been steady
and we are still pretty much
on time.  
w
E
E
K
1
7
We are located at:
128 East Main Street
Irwinton,GA
478.946.2818
478.233.1548
Week 17.
Outside colors have been chosen.  The
green is the tinted primer.  The front and side
steps are complete. The balcony is boxed in
and the handrail is finished. Everything is
almost complete inside.  The painters are
finishing up with the interior paint and should
finish the outside next week.